Case Study
Commercial & OfficeCoreFirst Bank & Trust
Headquarters Total Renovation
Topeka, KS 35,717 SQ FT
Completed: November 01, 2020Originally chartered in 1959, CoreFirst Bank & Trust had occupied its iconic Topeka headquarters building since the 1970s. When it came time for a total renovation, everything was stripped down to the walls. McElroy’s was the Design-Build firm for all mechanical, electrical and plumbing (MEP) systems.
We replaced the entire mechanical plant, all plumbing and ductwork, and completely rewired the building. We installed three high-efficiency boilers, an air-cooled chiller, hydronic pumping systems and two variable-air-volume (VAV) air-handling units serving fan-powered boxes for zone control with hot-water reheat.
McElroy’s designed, installed and programmed the Solidyne building automation system. For added employee/customer safety and peace of mind, we installed an in-duct Ultraviolet-C air purification system.
PROJECT HIGHLIGHTS
- MEP Design-Build firm
- Completely replaced plumbing, ducts and wiring
- Total upgrade of mechanical plant
- Three high-efficiency boilers
- Air-cooled chiller
- Two VAV air-handling units
- Zone-control boxes, fan powered, hot-water reheat
- Ultraviolet-C air purification
- Installed/programmed Solidyne building automation